What’s New & What’s Improved
Action Plans
Add Implementation and Effective Dates to Action Plans: You can now add two new optional date fields – Implementation Date and Effective Date – to Action Plan tasks and subtasks to help you clearly track when corrective actions are implemented and when they take effect.
How to Enable:
- Open your Action Plan document and go to the Settings tab.
- Select “Enable Action Implementation Date.”
- Toggle the setting on to display the field in tasks and subtasks.
- Toggle “Allow Implementation Date to Exceed Action Plan Due Date” if you want to permit dates beyond the plan’s due date.
- Select "Enable Action Effective Date."
- Toggle the setting on to display the field in tasks and subtasks.
- Toggle “Allow Effective Date to Exceed Action Plan Due Date” if you want to permit dates beyond the plan’s due date.
What’s Fixed – Bugs We Squashed
- When an Action Plan is set to “Auto Close Findings: Close and Approval All,” the original Responsible Party on each Finding is now retained.
- Fixed an issue where mixed static and random questions did not appear in the correct order during assessments.
- Assessments with a “Not Started” status in the Assessment by Status report drill-down now correctly link to the Results page.
- Resolved an issue where text in certain assessment fields did not wrap properly.